All the interior timber stud walls are up. All stud for the interior walls is all made on site rather than prefab. 4×2 studs, full fill insulation and then 12.5mm plasterboard. Roof trusses are also starting to go on.
extension
All posts tagged extension
Second day for the crane and this time it was to lift up and in all the external wall panels. All panels are pre insulated and cut to size. This all go straight on the prefab floor and each panel is fixed to the next. Once these are up the internal stud work can be built to form the layout of the walls and rooms.not bad for 2 days work.